Four major roadworks projects to start on the N4

Trans African Concessions (TRAC) takes pride in being the concessionaire of the Maputo Corridor and is committed to keeping the entirety of this international route in pristine condition and on par with world standards.

For this reason, we continuously implement construction projects along the route. These not only allow us to conduct routine road maintenance and rehabilitation of what already exists but also provides the opportunity to do major upgrades such as building additional lanes on the road as well as the construction of interchanges and bridges.

Apart from the Schoemanskloof upgrade and rehabilitation project that is already underway, TRAC will also commence with four new projects along the N4:

Schoemanskloof (N4-6Y km 2.7 to km 62)

Upgrading and rehabilitation of Schoemanskloof

  • Commencement date: October 2024
  • Expected completion date: October 2027
  • Progress of completion: 10%
  • Traffic accommodation: Shoulder and/or lane closures and stop/go closures
  • Main contractor: TauPele

Crocodile Gorge Upgrade (N4-7 km 74.1 to km 90.05)

Upgrading to four lanes and rehabilitation of the existing N4

  • Commencement date: April 2025
  • Expected completion date: February 2028
  • Progress of completion: Construction to start in March 2025
  • Traffic accommodation: Shoulder and/or lane closures
  • Main contractor: Raubex Construction

Hectorspruit to Lebombo Border Post (N4-8 km 45.55 to km 70.23)

Rehabilitation of the existing N4

  • Commencement date: March 2025
  • Expected completion date: December 2026
  • Progress of completion: Construction to start in February 2025
  • Traffic accommodation: Shoulder and/or lane as well as stop/go closures
  • Main contractor: Roadspan/WBHO JV

Ressano Garcia Border Post to Moamba Interchange (EN4-1 km 0 to km 41.29)

Rehabilitation and the construction of a new passing lane

  • Commencement date: October 2024
  • Expected completion date: December 2027
  • Progress of completion: Construction to start in February 2025
  • Traffic accommodation: Stop/go closures
  • Main contractor: WBHO

Moamba I/C to Tchumene Interchange (EN4-2 km 0 to km 25)

Pavement rehabilitation

  • Commencement date: Construction to start February 2025
  • Expected completion date: August 2025
  • Progress of completion: 0%
  • Traffic accommodation: Daytime stop/go closures
  • Main contractor: TC Projectos LDA

Although TRAC endeavours to prevent traffic disruptions due to road construction, traffic flow may be affected in certain areas, at specific times, and during peak traffic time. Therefore, we urge road users to visit our website for regular, real-time updates to assist in planning trips accordingly.